The Talgo Avril, designated Class 106 by Renfe, is a high-speed trainset built by Talgo. Its name stands for "Alta Velocidad Rueda Independiente Ligero," which roughly translates to "Light High-Speed Independent Wheel." The trainset operates in a top and tail configuration with power cars at both ends.

History

Talgo first showed its Avril concept at the Berlin InnoTrans fair in September 2010. The prototype, called G3, got Spanish approval on 13 May 2016 after covering over 76,000 kilometers and hitting 363 km/h. The first production order came in November 2016, when Renfe Operadora signed a €786.5 million deal for 15 standard-gauge trainsets plus 30 years of maintenance. In May 2017, Renfe ordered another 15 variable-gauge sets for €495 million, expecting them to start service in 2021, but that slipped to March 2024.

Renfe demanded €116 million in compensation from Talgo for the delays, later adding another €50 million and €80,000 per day for each day past 1 April 2024. During homologation testing, an Avril train reached 360 km/h on the Ourense-Santiago de Compostela high-speed line using Iberian gauge. In October 2019, infrastructure manager Adif bought a single variable-gauge set for €39 million to use as a diagnostics train. French operator Le Train ordered 10 trainsets with 30 years of maintenance in 2023 for €300 million.

From 21 May 2024, Renfe launched new AVE services to Asturias and Galicia using variable-gauge Avril trains, replacing Alvia routes like Madrid-Gijón and Madrid-Vigo. The Avril was also set to replace Class 102 trains on Avlo services connecting Madrid with Barcelona, Valencia, Alicante, and Murcia-Valladolid. In July 2026, Renfe and Talgo resolved their dispute over late deliveries and technical issues, freeing up roughly €200 million in withheld payments.

Renfe agreed to spend €132 million retrofitting its 15 standard-gauge sets with variable-gauge bogies, making the whole 30-train fleet uniform. Talgo’s €116.6 million penalty for late delivery was restructured, with repayments pushed back to 2032.

Design

The AVRIL is designed for a service speed of 330 km/h and a top speed of 380 km/h. It uses a power car at each end, with equipment mounted under the floor and on the roof, plus twelve intermediate trailer cars.

This layout gives it a passenger capacity similar to an electric multiple unit, not a locomotive-hauled train. Each trailer car is 13 meters long, and the whole train is 3.2 meters wide, allowing for a standard 3+2 seat layout. Versions are planned for fixed gauges of 1,435 mm, 1,520 mm, or 1,668 mm, as well as variable gauge.

The traction system works with four voltages: 25 kV 50 Hz, 15 kV 16.7 Hz, 3 kV DC, and 1.5 kV DC. The production trains look quite different from the prototype, losing the distinctive duck-bill nose. Talgo switched from ABB to Ingeteam for traction converters and TSA for traction motors. Renfe’s trains include 11 toilets, two wheelchair spaces, and seat-back display screens.

Technical issues

Since entering service, the train has experienced numerous incidents including power failures and software issues. On 5 August 2024, an Avlo train with 494 passengers was delayed two hours in the Madrid Chamartín-Atocha tunnel due to a power failure, with interior temperatures reaching 40 °C and passengers breaking windows for ventilation. Renfe apologized and blamed Talgo. On 1 January 2025, the trains failed to start because a software issue in the battery charging system did not recognize the change in year; the issue was resolved the next day.

In July 2025, routine inspections found cracks in the motor bogie of a power car on an Avlo train operating Madrid–Barcelona services, leading to the withdrawal of all five trains used for that service. Drivers reported vibrations and irregular movements at speeds up to 310 km/h. A speed limit of 250 km/h was imposed on a 190 km section from Madrid-Atocha to near Calatayud. Persistent technical and signalling incompatibilities with France's LGV Sud-Est blocked international certification; Renfe cancelled its framework agreement with SNCF Réseau in April 2026, handing back reserved train paths and suspending planned services to Paris.

More in High-speed Trains

Sources

Compiled from Wikipedia and the sources listed below. Text from Wikipedia is available under CC BY-SA 4.0; this entry is adapted from it.

Spotted an error? Know more?

Reader corrections go straight into our review queue. Suggest an edit · How this site is sourced

Comments

Loading…
Open in the interactive codex →